Project Management Professional | PMP | ادارة المشاريع الاحترافية Quiz 2
  إظهار بيانات الطالب   إظهار التعليمات   تغيير اتجاه الصفحة

رقم السؤال: 1           درجة السؤال: 1
 1. There is a cyclic nature to all projects.
 2. Problems will always occur in the execution phase.
 3. There are high expenditures during closeout.
 4. The bulk of the project budget will be spent in the execution phase.
رقم السؤال: 2           درجة السؤال: 1
 1. Reviewing the performance of an installed software module.
 2. Managing changes to the project schedule.
 3. Decomposing the WBS to a work package level.
 4. Performing a benefit-cost analysis to determine if we should proceed.
رقم السؤال: 3           درجة السؤال: 1
 1. Initiating, planning, expediting, and control.
 2. Plan, organize, develop, and control.
 3. Plan, do, observe, commit.
 4. Initiating, planning, executing, monitoring &controlling, and closing.
رقم السؤال: 4           درجة السؤال: 1
 1. project archives.
 2. a project charter.
 3. a project management plan.
 4. a risk analysis plan.
رقم السؤال: 5           درجة السؤال: 1
 1. Fixed price (FP)
 2. Cost plus percent of cost (CPPC)
 3. Time and material (T&M)
 4. Cost plus fixed fee (CPFF)
رقم السؤال: 6           درجة السؤال: 1
 1. Problem solving
 2. Forcing
 3. Withdrawal
 4. Compromising
رقم السؤال: 7           درجة السؤال: 1
 1. Control Scope and Validate Scope.
 2. Direct and Manage Project Work.
 3. develop project management plan and develop project charter.
 4. Develop Project Management Plan and Develop Schedule.
رقم السؤال: 8           درجة السؤال: 1
 1. Scope planning.
 2. Decomposition.
 3. Scope base lining.
 4. Bill of Materials (BOM).
رقم السؤال: 9           درجة السؤال: 1
 1. Identify Risks
 2. Perform Quantitative Risk Analysis
 3. Plan Risk Responses
 4. Control Risks
رقم السؤال: 10           درجة السؤال: 1
 1. you are over budget.
 2. you are ahead of schedule.
 3. you are only progressing at 76 percent of the rate originally planned.
 4. you are only progressing at 24 percent of the rate originally planned.
رقم السؤال: 11           درجة السؤال: 1
 1. Company processes
 2. The company culture
 3. Historical WBSs
 4. Project scope statement
رقم السؤال: 12           درجة السؤال: 1
 1. at this time, we expect the total project to cost 89 percent more than planned.
 2. when the project is completed we will have spent 89 percent more than planned.
 3. the project is only progressing at 89 percent of that planned.
 4. the project is only getting 89 cents out of every dollar invested.
رقم السؤال: 13           درجة السؤال: 1
 1. occurs before administrative closure.
 2. is the only one to involve the customer.
 3. includes the return ofproperty.
 4. may be done more than once for each contract.
رقم السؤال: 14           درجة السؤال: 1
 1. meeting and exceeding the customer's expectations.
 2. adding extras to make the customer happy.
 3. the degree to which the inherent characteristics fulfill requirements.
 4. conformance to management's objectives
رقم السؤال: 15           درجة السؤال: 1
 1. mitigation.
 2. transfer.
 3. acceptance.
 4. avoidance.
رقم السؤال: 16           درجة السؤال: 1
 1. Team member.
 2. Customer.
 3. Stakeholder.
 4. Supporter.
رقم السؤال: 17           درجة السؤال: 1
 1. New product development.
 2. Project.
 3. Program.
 4. Enterprise.
رقم السؤال: 18           درجة السؤال: 1
 1. The project manager is responsible for employee skills improvement.
 2. The functional manager is responsible for employee skills improvement.
 3. The project manager is responsible for the employee.s annual appraisal.
 4. The employee is responsible for his or her own skills improvement.
رقم السؤال: 19           درجة السؤال: 1
 1. Initiating
 2. Before the project management process
 3. Planning
 4. Executing
رقم السؤال: 20           درجة السؤال: 1
 1. Forcing
 2. Smoothing
 3. Compromise
 4. Problem solving


   