Project Management Professional | PMP | ادارة المشاريع الاحترافية Quiz 4
  Student data   Test instructions   Page direction

Q1           Score:  1
 1. 0.75
 2. 1.50
 3. 0.25
 4. 1.15
Q2           Score:  1
 1. Perform a design of experiments.
 2. Adjust the chart to reflect the new mean.
 3. Find an assignable cause.
 4. Nothing. This is the rule of seven and can be ignored.
Q3           Score:  1
 1. PERT analysis
 2. GERT analysis
 3. Monte Carlo analysis
 4. Critical path method
Q4           Score:  1
 1. The project plan.
 2. The project goals and objectives.
 3. The project charter.
 4. The project definition.
Q5           Score:  1
 1. Reduce the time needed to do the project.
 2. Increase the total time necessary to do all the tasks.
 3. Reduce the overutilization of resources.
 4. Reduce resources to the lowest skill that is possible.
Q6           Score:  1
 1. Project management plan
 2. Communications management plan
 3. Configuration management plan
 4. Quality management plan
Q7           Score:  1
 1. Check risk status.
 2. Check cost performance.
 3. Check progress reports.
 4. Tell the team your objectives.
Q8           Score:  1
 1. Projectized organization.
 2. Strong matrix organization.
 3. Weak matrix organization.
 4. Balanced matrix.
Q9           Score:  1
 1. $100,000
 2. $114,500
 3. $117,000
 4. $119,500
Q10           Score:  1
 1. 1
 2. 3
 3. 0.85
 4. 2
Q11           Score:  1
 1. confronting.
 2. compromise.
 3. smoothing.
 4. forcing.
Q12           Score:  1
 1. Initiating
 2. Executing
 3. Planning
 4. Closeout
Q13           Score:  1
 1. withdrawing.
 2. directing.
 3. organizing.
 4. controlling.
Q14           Score:  1
 1. Alert the project sponsor of potential impacts to cost, scope or schedule.
 2. Qualify the risk.
 3. Mitigate this risk by developing a risk response plan.
 4. Develop a workaround.
Q15           Score:  1
 1. Validating scope
 2. Controlling the schedule
 3. Performing Change Control
 4. Manage Stakeholder Engagement
Q16           Score:  1
 1. Earned value (EV)
 2. Planned value (PV)
 3. Actual cost (AC',
 4. Cost variance (CV)
Q17           Score:  1
 1. The project is incomplete because the project needs to be re-planned.
 2. The project is incomplete until all the activities required for closing a project are completed.
 3. The project is complete because the customer has accepted the deliverables.
 4. The project is complete because the project has reached the due date.
Q18           Score:  1
 1. verbal
 2. written
 3. formal
 4. nonverbal
Q19           Score:  1
 1. The number of days the project will be late divided by the project duration
 2. The percent of time a given activity will be on the critical path
 3. The percent of time an activity will be late
 4. The sum of the duration of the critical path activities divided by the project expected value for duration.
Q20           Score:  1
 1. Project Appraisal.
 2. Monitoring and Controlling Process.
 3. Planning Process.
 4. Progressive Elaboration.


   



Questions you haven't answered yet:


Are you sure you want to end this test and send your answers?

  


All copy rights reserved © arab-exams.com
  2014-2023